11/05/2026
🚧Greenbelt Construction Update🚧
The Boise River Greenbelt improvement project to repair and replace sections of the pathway located near Wood Duck Island off Boise Avenue is well underway. The existing asphalt paths are being replaced with concrete, creating a smooth surface.
The contractor has completed work on the two westernmost sections outlined in the project scope, which are now open for use. Demolition is now underway on the middle portion of pathway. Please stay out of any fenced or closed areas for your own safety. Fencing will be removed as each section is completed and reopened.
The project remains on schedule with completion expected by the end of 2026. Thank you for your continued patience and cooperation as crews complete these important pathway improvements.