06/02/2026
The construction of the Riverbend Athletic Complex is making visible progress! 🏗
Construction began in October 2025. Fast forward seven months.. Milestones are in reach.
Mass Grading is 95% complete.. Almost there!
Woodruff’s first roundabout is nearly complete, and Godfrey Town Road is progressing as curb installation continues-you can now see the outline of the road!🛣
The fields are starting to take shape as concrete work for the retaining walls on the East field is officially underway!
The vision is starting to become reality! 👀
Soon.. the Riverbend Athletic Complex will be welcoming the community.