05/11/2026
We are officially 11 days away from opening day! Over the past couple of weeks, the Bee Meadow Pool splash pad has undergone a massive transformation! Crews have installed our above-ground water features and finalized the internal plumbing. This week, over 40 ground jets, including fan jets, crown jets, and fountain jets, will be set in concrete now that their plumbing and connections are complete.
Beyond the pad, the site is coming together quickly! The perimeter fencing and baby pool sail shade are in place, and we’ve completed grass seeding to restore the landscape. Over the next few days, work continues on the remaining baby pool elements, entrance gates, and the specialized cargo net fencing that safely divides the 6 & Under section from the main splash pad area. Finishing touches are also underway, as the baby pool will be painted and the new benches will be installed around the splash pad to finalize the space.
The final major milestone begins this week as a lead technician from VakPak, the company that engineered our mechanical systems, flies in to commission our system launch. This involves the startup and calibration of the recirculation systems, feature pumps, manifolds, and disinfection systems, including the critical electrical interlocks that ensure everything communicates and operates safely. This work spans our mechanical room, outdoor cabinets, and rain diverter vaults.
To prepare for opening day, our management team, Eddie and Amanda, will be undergoing hands-on training with this lead technician to learn the ins and outs of these new systems. We are officially in the home stretch, with work continuing around the clock to make sure everything is fully tested and ready for action! We can’t wait to kick off our most exciting summer yet, see you at the grand opening! ☀️😎