07/16/2023
Dredging Update From Schuylkill Navy
Read & heed
FOR IMMEDIATE DISTRIBUTION TO ALL MEMBERS AND COACHES WITHIN SCHUYLKILL RIVER-BASED ROWING/PADDING PROGRAMS
* Per our discussion yesterday, coaches/ coxswains/ bowperson of each program should review to ensure their situational awareness of all equipment on the river related to the dredging.
Key Summary:
* All boats should always keep EAST of the dredge equipment (ie, The Dredge Providence, Booster Pumps, 3 1/2 Mile Pipe (ie, keep the dredge equipment off your port side when travelling upriver).
* The pipe dynamically floats to the surface and sinks below it when material is pumping through it. It's possible to accidentally cross the pipe where it's submerged.
* If you do not have the dredge equipment (and, most importantly, the pipe) TO THE WEST OF YOU at all times, you will likely get trapped "within" the pipe.
EFFECTIVE AS OF FIRST LAUNCHING ON MONDAY MORNING JULY 17TH 2023.
* The western-most arch (typical, upriver arch) of Strawberry Mansion is CLOSED until future notice.
* ALL traffic moving upriver on the west side should move east into Lanes 5 & 6 at the 1000 m mark (middle of Gillin Boat House (SJU/SJP).
* Proceed upriver in Lanes 5 & 6, leaving Lane 4 as a Dead Lane.
* Upriver traffic may move back to the western, upriver travel lanes (Lane 7 and towards the western shore) 200 m upriver from the Dredge's location.
* ALL Downriver Traffic from Twin Stones through the upriver end of Peter's Island should be confined to ONLY Lanes 1-3, with 100% of downriver traffic moving through the Lane 1-3 arch of Strawberry Mansion Bridge.