12/05/2025
Bathrooms & Locker Rooms Update
What Happened Today:
Our plumbing and construction teams were onsite to locate the source of the issue. After extensive work cutting through concrete, they determined that the damaged pipe is located beneath the women’s bathrooms and locker rooms. This discovery required over seven hours of investigation, and the team reached a stopping point for the day.
What’s Next:
Repair efforts will continue Saturday morning, when contractors will begin opening the flooring to access and fix the damaged pipe. Once Saturday’s work is completed, we will provide a detailed update on the new projected timeline.
Additional Note:
The issue is being addressed by our landlord and all repairs must be coordinated through them and their contractors. We appreciate the patience, understanding, and support our community has shown throughout this disruption. Your messages, recommendations, and willingness to help speak volumes and we appreciate all of it.