Onawa Bowl

Onawa Bowl Bowling, Bar and recreation The restoration and build out of Onawa Bowl is to commence this spring 2017. Hours of operation will be posted once open.

The center comprises of 8 AMF 8270 bowling equipment, bar and recreation area. Pool, dart, bowling leagues will be formed after opening. The open hours will be adjusted as the Center progresses. Construction time is currently TBD while a list of the necessary build out features are determined.

08/10/2023

Update: Our current schedule has us opening by the end of the year. Time will tell.
Thanks

09/23/2018

Update:

For those that would like to skip the details; Opening date remains TBD.
The installation of the replaced materials and new lay-up concluded in late March. A slowdown was experienced shortly afterwards due to equipment issues and an injury at home. I am now working on wrapping up the 2 bathrooms and kitchen.
Since my guesstimates have proven to be too aggressive and wishful thinking, they have been removed from the posts to save on confusion.

Details:

Shortly after the installation of the replacement materials, the above average temperatures this Spring mixed with equipment issues made daytime work impossible...Usually starting after 1AM if it cooled down enough. After several incorrect parts from the manufacture, the portable equipment was finally up and running 8 weeks later. This was followed by an injury at home to my hand this summer that took me down for a while. After 4 weeks, I was able to return to work at 80% level while the nerve damage continues to heal. A full recovery is expected in the months to come.
As stated in the last post, we were looking at the impacts due to the delay of switching manufacturers for materials. That shift now added with equipment issues and an injury, caused us to fall off the schedule with the subs which forced us to reorganize and devise a work around. The subs are now working to a fit us in here and there. Unfortunately we are at their mercy, but they are doing well at fitting us in. I am currently working around the subs as they progress on their work. I have the bathrooms and kitchen built and nearly ready for finish work once the subs complete their tasks.

As usual, better news too. To give a more reliable and fun bowling experience, the original plan included an upgrade of the bowling equipment after re-opening. However, I used the setbacks to work on implementing this now. It has been designed, proto-typed, tested and sent to manufacturing. This upgrade replaces the 1970's logic with a μProcessor controller and solid state motor drivers.
What this means is the bowling machines will now communicate with the scoring system - getting rid of 10th frame manual resets and gutter/single pin resets. Additional features added are pin count redundancy, increased efficiency, pin distributor monitoring, self-diagnostics, front desk trouble alerting, full electronic machine control, maintenance indicators and much more. Burn in of the new controllers and shake down of the new design will be done once the new boards are assembled.

While I do not have pictures prior to the start of remodeling, attached are 2 ‘Before’ pics. These show the work that was done on removal of what was left of the ceiling, inspecting/cleaning the upper trusses, re-supporting necessary areas and painting. As you can tell lots of cleanup was completed after that. Working around the disassembled machines was a nightmare. Much better now since they are back to their original locations. The other 2 pictures named ‘After’ is a look over the bowling area and entrance taken in April. Sorry for the dim lighting. We are working with portable equipment while the subs finish their work.

More to come.

01/10/2018

We hope everyone had happy holidays!

An update on progress:

November was great once again. Moved forward very well.

December took a different path. We ran into bad material. After several visits from our vendor, the end result was taking a few steps backwards and removing what was just installed and sending all of our stock back. Then ordered replacement materials from a different manufacturer. The new material is a different type/size which also meant a layup change. The replacement materials arrived the last week of December. Since then, we have been moving quickly although we have found that the new layup takes longer to install then the original layup. Currently this phase looks to be done mid-February. It was original progressing on schedule for the end of December prior to running into the bad material.

Obviously this unfortunately does mean a slip in our schedule. Approximately 6-8 weeks.

Not all bad news for December. While waiting for our vendor to process the return and get the new materials ordered and delivered, I proceeded to work on cleaning the pinsetters, remounting the heads and assembly. All heads have been remounted and lanes 6-8 are re-assembled. Had just enough time to get lane 8 fired up. With just a few tweaks-ready to bowl! I didn’t keep score while test bowling. Let’s just say I’m out of practice.

Once we are done installing the new material, we will have another update with some interior pics.

Thanks for your patience and understanding. We are just as disappointed about the delay.

Progress update -These sidewall sheets where hung in early October. However the trim was not yet in. Finished it up once...
11/09/2017

Progress update -
These sidewall sheets where hung in early October. However the trim was not yet in. Finished it up once the trim arrived later in October. This would be the South-East side of the building.
For those that are interested, the picture with the laser line - the laser has an accuracy of ±1/16" at 100ft. After a decade of the building enduring winter/summer without temperature control, the buildings is within an 1/8" level from end to end (126ft). Not bad considering that is what it was built to almost 2 decades ago.

I did not have previous pictures prior to starting the inside refurbishment. I have collected some pictures now, so once additional progress is completed, I will be posting those here.

Everything is progressing very well. I was hoping to make up lost time from the hot summer months, however this did not happen. I will let everyone know more as things continue to progress.

I have been asked to possibly post some photos as progress continues. As of this week, the outside of the building is in...
10/06/2017

I have been asked to possibly post some photos as progress continues. As of this week, the outside of the building is in work. Pictured is a before, a new sheet being loaded and an after shot of the roof. 8 sheets total where replaced in 2 areas.
More to come.

06/12/2017

Update:
Our house has closed and we have moved in. Still have some small things to do there.
Renovation of the alley has commenced. A couple weeks later than originally intended, however we did make late spring. Summer is just around the corner.
Opening date is TBD. A specific date will reveal itself as the remodel progresses.

03/25/2017

Final designs to be completed in April. This puts re-modeling of the alley to commence shortly after that. Sometime in May!

02/02/2017

Long lead items have been ordered. Continue to be on schedule for re-modeling to begin later this spring!

10/22/2016

Taking suggestions on the re-model that is commencing soon. Tell us what you like! We will consider it.

https://www.facebook.com/OnawaRec/
___________________________________________________
Thank you to everyone for your suggestions!
These will certainly help us provide the services that best suit everyone.
While we will make every effort to implement everything we can, we are working within the constraints of an existing layout. We will do our best to utilize what is available to us as we remodel the facility.
In the meantime, please be understanding in that it will take some time to have the establishment refurbished and re-opened. Once we have a final design laid out, we will begin actual construction later this spring.

Once a re-open date is realized, it will be posted here and at the alley along with hours of operation.
Prior to opening, we will be asking for additional feedback to marry themes to certain days/nights. Any special shoe requests can be made at that time as well.
The center will house the existing 8 lanes with black lights, foggers, automatic scoring and additional upgrades. The lanes will be UV black light reactive.
As we lock in other enhancements, we may post them here or leave them as a surprise on your first visit!

Once open, we will continue to monitor operating hours and themes. If any changes are necessary, either by popular demand or addition of other activities, they will be announced well prior to implementation.
League sign-up sheets (bowling, dart and pool) will be posted at that time as well.

As the center becomes established, we will be looking into expansion options to house additional activities.

You are welcome to continue to leave comments.

09/18/2013

Acquisition of current structure and lanes was completed Friday.

Address

500 9th Street
Onawa, IA
51040

Website

Alerts

Be the first to know and let us send you an email when Onawa Bowl posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Share