03/31/2026
Update on construction:
PLAYGROUND: Drainage and grading work is occurring on site to prepare the subsurface. Equipment foundations are being prepared and installed. Next steps: Final drainage will be complete once dry weather occurs for a few days. Once foundations are complete, equipment will start being installed. The project remains on track for overall completion in the May–June timeframe.
GAME COURTS: The tennis court will close and the access fencing and divider fence mesh will be removed by the end of March. Milling and removal of existing footers will begin in early April, and by mid-month, fine grading and proof rolling of the subbase, installation of base course and new footers, and placement of wearing course (asphalt surface) should all be under way or completed. Following installation of the wearing course, a curing period will be required. Acrylic court surfacing will be applied approximately 30 days after the wearing course has fully cured to ensure optimal performance and longevity. Expected project completion June.