09/03/2026
🏗️ PROGRESS UPDATE: We’re getting closer! 🏗️
August was a major month of progress at the Prisma Health Performance Center! From setting chillers and AHUs onto the roof to completing metal panels and paving the main parking lot, the venue is taking shape fast.
Here is what was accomplished in August:
-Rooftop Lifting: Chillers set and Air Handling Units (AHUs) lifted to the roof.
-Exterior Milestones: Completed metal paneling, finished fireproofing, and poured stair treads.
-Site Infrastructure: Parking lot paving started, underground utilities set, and Duke site lighting poles set.
Looking ahead to September, the team will start landscaping and sod installation, power up the AC, and begin athletic equipment installation.
Stay tuned for more behind-the-scenes updates as we build the Prisma Health Performance Center! 🏀🏐