09/08/2026
The next several weeks will be very busy with all the ongoing projects.
Update on what to expect:
1. F&B Drive Thru Barn is progressing nicely. Trusses are up and now starting on the back porch.
2. Pad has been poured for the 20 Bay TopTracer Facility. Cover The Tees will be here Sept 21 to install the building. Once that is completed, TopTracer will be here to install the technology.
3. Light poles for back 9 lighting are being delivered today (9/8). Poles will then be staged before installation. Other than a few more junction boxes to be installed, everything else is ready.
4. Front cart path repair is set to begin any day. Once the back 9 lighting project is complete, we will start the back 9 cart path repair.
5. Fairway bunker renovation will begin next week.
6. Clubhouse expansion/renovation will begin as soon as the F&B drive thru barn is completed.
Please be prepared for a hole being played as a par 3, for a hole closure, a back or front 9 closure or the possibility of the course being closed.
The practice range remains closed at this time. We will post here if we are able to open the range for a particular day.
Please call ahead for a tee time!
Thanks for your continued patience during this time.