Construction Progress Update (as of August 26, 2026)
The Start to the Heart (Abingdon to Damascus) section of the trail remains open and welcoming trail lovers!
Virginia Creeper Trail Reconstruction:
-Slope Failure 10 was completed on Aug. 15, 2026.
-Permanent Bridge 34 was set on Aug. 18, 2026.
-Permanent Bridge 35 was set on Aug. 17, 2026.
-Permanent Bridge 44 was set on Aug. 20, 2026.
-Permanent Bridge 45 was set on Aug. 20, 2026.
-Bridges 26 and 37 are next to be set.
-Thirty-seven of 56 concrete bridge abutments have been poured.
-Eight bridge decks had been poured as of Aug. 22, 2026.
-Bridges 22, 23, 29, 30, 31 and 32 are complete, with decks and curbs installed.
-Seven of eight H-piles at Bridge 27 had been installed as of Aug. 24, 2026.
-Twelve of 13 culverts in Segment 7 had been installed as of Aug. 24, 2026.
-Culvert removal and installation are ongoing in Segments 3, 4, 5, 6 and 7.
------------
Taylor’s Valley Waterline:
-8,200 of 9,100 linear feet of ductile iron pipe had been installed as of Aug. 24, 2026.
-Horizontal directional drilling (HDD) for the waterline project is now complete.
More construction updates from Kiewit Corporation can be found at CreeperTrailRebuild.com