Construction Progress Update (as of June 16, 2026)
The Start to the Heart (Abingdon to Damascus) section of the trail remains open and welcoming trail lovers! đź’š
The first permanent concrete pour was completed at Bridge 16, Abutment 1 and Bent 1, on June 10, 2026. Concrete pours will continue at additional bridges.
Work at Slope Failures 2 and 3 is nearing completion.
Thirteen of 23 bridges have been fabricated at Contech, with eight delivered to the site.
151 of 213 micropiles have been installed. Micropile installation is now complete in Segments 4 and 5.
Twelve of 21 H-piles have been installed at Bridge 16.
-----------
Taylor’s Valley Waterline Replacement:
One of four directional drill sections is complete, and the second directional drill is more than 75% complete.
More than 3,600 feet of ductile iron pipe has been installed by Kiewit and subcontractor ASI.
Hydrostatic pressure testing is ongoing for installed waterline segments to confirm there are no leaks.
More construction updates from Kiewit Infrastructure South Co. can be found at CreeperTrailRebuild.com