06/05/2026
Work on the new compressor room continues, and the space is really beginning to take shape as crews progress with the construction of the block walls.
The second layer of floor insulation is also nearing completion in preparation for the installation of the refrigeration piping system. Concrete work at the ice resurfacer door has continued as well, following the installation of the main refrigeration piping.🥅
📸 Take a closer look at some of the latest work, including the concrete pour at the ice resurfacer entrance, the refrigeration header trench that will support the arena's cooling system, and the new compressor room as it continues to come together.
We're excited to see the project progressing and look forward to sharing more updates as construction continues.
🏒❄️👷♂️