05/06/2026
This week has seen massive strides towards completion - track fully tarmacked and loads of turf laid. It’s likely that construction will be complete by the end of next week once a fence is installed, signage put up and turf finished off.
Before we can open it to the public a safety inspection needs to be completed - this could happen end of next week but no guarantees. You’ll know when it’s open when the heras fencing is removed!
We think the team from Forte Trailscapes have done an amazing job so far, check out these latest images!